If a bathroom floor in a raised timber house slopes because the stumps or bearers underneath have moved, fix the subfloor before the new waterproofing and tiles go down. A tiler can build a fall to the waste on a stable floor, but no tile bed stops the structure under it moving, and a wet area laid over a moving floor is at risk of cracked grout, failed sealant and water in the subfloor. The order is: assess the subfloor, restump or relevel, confirm the floor is level, then waterproof and tile.
Structural slope or just old tiling?
Two different slopes get confused. A fall to the waste is a deliberate slope the tiler builds into the tile bed so water runs to the drain. A structural slope is the floor frame itself sitting lower in one place because a stump has sunk, rotted or lifted.
Simple checks before any quote:
- Put a spirit level on the hallway or the next room. If the slope carries on past the bathroom door, the cause is under the floor, not in the tiles.
- Look for the company it keeps: sticking doors, gaps under skirting boards or a floor that feels bouncy.
- Get under the house, or have someone do it, and look at the stumps under the bathroom bay for leaning, crumbling or soft timber.
CSIRO’s homeowner guide explains why timber floors move unevenly: isolated piers under the floor rise more easily than the footings under walls when clay swells, giving a domed floor, and drying lowers the outer footings first. Piers that lose contact with their bearers leave a floor that feels bouncy (CSIRO, Foundation Maintenance and Footing Performance). The uneven and sloping floors guide and the signs your house needs restumping guide go through the symptoms.
One shortcut to avoid: packing extra blocking between a bearer and a stump that has dropped. CSIRO warns that when the clay next swells, the extra blocking can push the floor up into a dome; if blocking is used, it suggests a pair of fine wedges and fortnightly monitoring.
Fix the subfloor first
Where a stump has failed or sunk, restumping replaces it on a new footing; where the stumps are sound but the floor has drifted, house relevelling brings bearers and joists back to level. For a single bay under a bathroom, whatsthedamage.com.au’s national restumping guide (updated November 2026) lists partial restumping or a spot relevel of 5-10 stumps at $2,200-$5,600, typical $3,600, prices including GST. That is a national figure, not a Wagga price; the underpinning cost guide has the other published figures.
While the floor is open, the subfloor’s condition matters for the new bathroom too. CSIRO notes that poor subfloor ventilation causes condensation and that damp subfloors suit pests including termites, and recommends adequate ventilation. Where the floor is still moving, a foundation inspection first tells you whether the bathroom slope is a local stump problem or part of wider movement.
Waterproofing and licences
Waterproofing of domestic wet areas is covered by AS 3740-2021, which Standards Australia’s store lists as current and describes as setting minimum requirements for the materials, design and installation of that waterproofing (Standards Australia, AS 3740-2021). However well the membrane is applied, it relies on the floor under it staying put.
In NSW, “Waterproofing”, “Wall and floor tiling” and “Underpinning and piering” are each listed as trade work, which needs a contractor licence for residential work over $5,000 including labour and materials, while plumbing and drainage is specialist work that needs a licence regardless of cost (NSW Government, Categories of building and trade work). Work over $5,000 including GST also needs a written contract, with a deposit of no more than 10% (NSW Government, Contracts). Check each licence on NSW Fair Trading.
The order of trades
| Stage | Who | What happens |
|---|---|---|
| 1. Subfloor assessment | Licensed builder, restumper or inspector | Stump condition, floor levels, whether movement is still active |
| 2. Restump or relevel | Licensed contractor | Floor frame brought back to level on sound supports |
| 3. Re-check the floor | Same contractor | Levels confirmed across the bathroom bay |
| 4. Strip out | Builder or tiler | Old tiles, membrane and damaged sheeting removed |
| 5. Plumbing rough-in | Licensed plumber | Waste and supply positions set to the new floor level |
| 6. Waterproofing | Licensed waterproofer | Membrane to AS 3740 on a stable substrate |
| 7. Tiling and sealing | Licensed tiler | Fall to waste, tiles, grout and flexible sealant joints |
Two practical points. The restumper needs clear access under the floor, so book the subfloor work before demolition, not after. And the tiler should not start until the membrane maker’s curing time has passed; the product’s data sheet sets it.
Frequently asked questions
Can the tiler just use extra mortar to fix the slope?
On a stable floor a tiler can build up the bed to get the fall right. If the floor frame is still moving, a thick bed over timber is likely to crack with it, so confirm the floor is stable first.
Does the plumber need to come back after relevelling?
Usually, at least to check the waste and fittings against the new floor level. Allow for it in the plumbing quote rather than finding out on the day.
Does a bathroom renovation need Council approval?
It depends on the scope and the property. Ask Wagga Wagga City Council or an accredited certifier before work starts, and ask the builder who will arrange it.
Request a quote for the subfloor side of the job; if your enquiry is referred, an independent licensed contractor inspects and quotes in their own name.
Sources
- CSIRO: Foundation Maintenance and Footing Performance (2024, PDF) (doming of timber floors, blocking, subfloor ventilation), checked 15/11/2026
- whatsthedamage.com.au: Restumping and reblocking cost (updated November 2026), checked 15/11/2026
- Standards Australia store: AS 3740-2021 Waterproofing of domestic wet areas (published 23 July 2021, status current), checked 15/11/2026
- NSW Government: Categories of building and trade work, checked 15/11/2026
- NSW Government: Contracts for residential building work, checked 15/11/2026
- NSW Fair Trading: Home building licence check, checked 15/11/2026