Guide

Concrete Underpinning: How the Method Actually Works

Wagga Foundation Repairs is an independent referral service and does not perform or contract for the advertised work. Your enquiry may be referred to an independent contractor. Where licensing is required, the contractor's identity and licence details will be provided before you accept a quotation or enter a contract.

Concrete underpinning (also called mass concrete or traditional underpinning) supports a footing that has dropped by digging pits beneath it, one section at a time, and filling each pit with concrete so the footing bears on firmer ground deeper down. The NSW Government describes underpinning as building a new support structure under a wall, column or footings without removing the building above (NSW Government, Underpinning and piering work). The pit positions, depths and sequence come from a structural engineer’s design, not a standard recipe.

The step-by-step: excavate, pour, cure, repeat

Concrete underpinning is a series of separate stages, repeated at each pit along the affected footing:

  1. Design. The engineer works from a crack and floor level survey and usually a soil report, and specifies the number of pits, their positions and size, the founding depth and the order of work. The underpinning depth guide explains how the depth is set.
  2. Before digging. A free enquiry with Before You Dig Australia shows indicative locations of underground services; its plans are indicative only and are not approval to excavate. In Wagga, building over or near a Council sewer or stormwater main needs a separate application that includes detailed structural designs of the footings (Wagga Wagga City Council, Building near sewer or stormwater lines).
  3. Excavate the pit. A pit is dug beside and then under the existing footing down to the founding layer the engineer specified. SafeWork NSW’s excavation code says excavation below a footing that could affect a structure’s stability should be assessed by a competent person and secured by a designed ground support system (SafeWork NSW, Code of Practice: Excavation work).
  4. Pour the concrete. The pit is filled with concrete to the underside of the existing footing. Mainmark, a contractor that sells resin injection as an alternative, says on its Sydney page that concrete “can take several days to get to strength” (Mainmark).
  5. Pack the top. The gap between the new concrete and the old footing is packed tight, as the design specifies, so the load passes into the new pit.
  6. Backfill and move on. The pit is backfilled and the crew moves to the next section in the planned order.

Backfill matters. CSIRO’s homeowner guide says that where soil next to footings has been washed away, soil of the same classification should be put back “compacted to the same density” (CSIRO, Foundation Maintenance and Footing Performance), and Mainmark warns that poorly compacted soil beside an underpin can act as a water path to its underside.

The hop-scotch sequence and why it matters

The most common question about this method is why the pits are not dug one after another along the wall. The reason is that the existing footing is carrying the house while the work happens. Digging under a long continuous run would leave too much of the wall unsupported at once, so the pits are dug in a staggered (hop-scotch) order: a pit is dug, poured and allowed to gain strength before the sections next to it are opened.

The SafeWork NSW code says excavation work “must not start” until steps are taken to prevent the collapse or partial collapse of a potentially affected building, and that suitable supports to brace the structure may also be required. Where the design calls for temporary props or needle beams, they go in before the pit is dug; the propping guide explains how. Work in or near a trench deeper than 1.5 metres is high-risk construction work that needs a safe work method statement under the same code. Ask each contractor to describe the sequence and support for your house before you sign.

When concrete underpinning is the right choice

The engineer chooses the method, but concrete underpinning is generally considered where:

  • A strip footing under masonry walls has dropped. Older brick homes on strip footings are the classic case, and the method extends the existing footing downwards.
  • Firm ground is within a practical digging depth. Each pit is dug, so the deeper the founding layer, the more digging, concrete and temporary support each pit needs.
  • Machinery cannot reach the work. Pits can be dug by hand where a piling rig cannot get in, which can suit tight side access.
  • The cause is dealt with too. A leak or downpipe wetting one wall is fixed as part of the job; see drainage and moisture correction.

When it isn’t, and what to use instead

  • The founding layer is deep. Screw piers are wound in mechanically to depth; the guide to screw pile versus concrete underpinning compares the two.
  • A slab has voids or has settled slightly. Resin or grout injection treats the ground under a slab without digging; see the resin injection guide.
  • Disruption matters. Pits remove paving and garden beds along the wall and take time to gain strength; Mainmark says traditional underpinning “could take a few days for a single underpin to several weeks”.
  • The movement is seasonal and the house is stable. Cracks that open and close with the weather may need moisture control and crack repair, not underpinning. A foundation inspection separates the two.

Cost drivers specific to concrete underpinning

Published prices are unit rates. Airtasker’s guide (15 October 2026) gives $1,500-$3,000 per linear metre for traditional underpinning, GST not stated, and Mainmark, a contractor, publishes $1,000-$3,000 per metre for mass concrete underpinning as its own figure (page modified 12 August 2026). Neither is a Wagga price.

Cost factorWhy it moves the price
Number and length of pitsSet by the engineer’s design; the rate multiplies by it
Founding depthDeeper pits mean more digging, concrete and support; Mainmark says deeper underpins cost more because each excavation needs shoring
AccessNarrow side access, low subfloors or internal pits slow the work
Temporary supportProps or needle beams where the design needs them
ReinstatementPaths, paving and garden beds over the pits
Engineering and soil reportOften priced separately from the pits

The underpinning cost guide has the full table of published figures with publishers and dates.

How long a concrete underpin lasts

No Australian standard or government page gives a service life for an underpin. Mainmark says on its Sydney page that concrete underpins “if well-constructed using sound concrete should last more than 50 years”; that is a contractor’s own claim. The bigger risk is the rest of the footing. Mainmark also notes that where only part of a footing on reactive clay is underpinned, seasonal movement can differ between the underpinned section and the rest, cracking the walls next to it. CSIRO says seasonal swelling and shrinkage of clay “affects the perimeter of the building first”, so drainage and watering around the whole house still matter after the work.

Concrete underpinning FAQs

Does concrete underpinning fully fix the problem?

It stops the underpinned section of footing from settling further. It does not close cracks or remove the cause of the movement, so crack repair comes afterwards and any leak or drainage problem needs fixing too.

How many pins does my house need?

The engineer decides, from the load on each section of footing, the depth to firm ground and the extent of the movement. A quote with no engineering basis for the number and spacing of pits is hard to compare with others.

Can I stay in my house during concrete underpinning?

Often yes, because the work is outside or under the floor and the house stays supported throughout. Expect noise, dug-up paths and areas to keep clear.

What is the difference between concrete underpinning and screw pile underpinning?

Both carry the footing on deeper ground. Concrete underpinning digs pits and fills them with concrete; screw piles are steel piers wound into the ground with a machine and bracketed to the footing.

Do I need council approval for concrete underpinning in Wagga?

It depends on the scope and the property. No official source found says underpinning is always exempt or always needs consent, so ask Wagga Wagga City Council or an accredited certifier before work starts (NSW Planning, Exempt development). The contractor needs an underpinning and piering licence for residential work over $5,000 including GST.

Request a quote

Sources

Last reviewed 16/11/2026. How these pages are researched and corrected.

More guides

Cornice Separation vs Ceiling Sag: Which Means Movement?

Cornice gaps and sagging ceilings have different usual causes. Which pattern can point to footing movement, which is…

View

Crack Width Gauge Guide: Measuring and Monitoring Cracks at Home

How to use a crack width gauge or tell-tale to monitor a wall crack at home, how long to watch it, what the readings…

View

Cracked Brick Walls in Wagga Wagga: Foundation Issue or Not?

How to tell whether cracked brick walls inside or outside a Wagga home point to footing movement: crack patterns,…

View

More on this topic

Request a quote

Tell us about the job and an independent local contractor can quote it.

Get a Quote