whatsthedamage’s national restumping guide (updated November 2026) says a standard three-bedroom house with accessible subfloor clearance takes about “4 to 7 working days on site”, including 24 to 48 hours for new footings to cure, and that low-clearance jobs where floorboards must be lifted take “7 to 12 working days” (whatsthedamage, Restumping & reblocking cost). A partial restump of a few stumps is shorter. Before the work come the inspection, quote, contract and any approvals; after it come floor coverings and crack repairs.
What sets the time on site
- How many stumps are replaced. A whole-house restump replaces every stump; a partial one replaces only those that have failed. whatsthedamage’s stump-count bands (5 to 10 for a partial restump, 15 to 25 for a two to three bedroom weatherboard, 25 to 40 for a standard three to four bedroom home) give a sense of scale.
- Subfloor clearance. Low clearance is the main reason whatsthedamage gives for its longer 7 to 12 day band, because floorboards may have to come up for access.
- What else is found. Rotted bearers or joists found once the crew is underneath have to be replaced as the job goes; whatsthedamage prices subfloor bearer or joist replacement as a separate per-metre item.
- Re-levelling. Bringing the floor back towards level is done in small, staged lifts. The house re-levelling page explains how a target is set.
- Access and weather. Narrow side paths, tight gates and garden beds against the walls slow the handling of stumps and concrete. Rain makes subfloor digging slower; Wagga Wagga AMO averages 8.9 days of 1 mm or more of rain in July against 4.2 in January (BOM, Climate statistics for Wagga Wagga AMO), so a winter start may need more contingency.
Before work starts
Several steps come before the first stump is dug, and some have fixed waiting periods:
- Inspection. A subfloor inspection decides whether restumping, re-packing or something else is needed; the guide to signs a house needs restumping explains what to look for.
- Quote and stump type. Concrete, steel or timber stumps are compared in the concrete stumps vs steel piers guide.
- Contract. Work over $5,000 including GST needs a written contract and a deposit of no more than 10%; over $20,000 there is a five clear business day cooling-off period (NSW Government, Contracts for residential building work), and the contractor should provide a home building compensation certificate before taking a deposit (Service NSW).
- Licence. Piering falls in the underpinning and piering licence category, needed for residential work over $5,000 including GST (NSW Government, Underpinning and piering work).
- Approval. Whether the job needs approval depends on the scope and the property; ask Council or an accredited certifier before work starts.
- Before You Dig. Before You Dig Australia members are “encouraged to respond within 2 business days” to an enquiry (BYDA, For Homeowners).
Do you have to move out?
Usually not, though the published guides do not cover it, so ask the contractor. While a section is jacked, its floor may be uneven, doors may not close properly, and water or gas may need to be disconnected for a period. Ask for a day-by-day plan showing which rooms are affected and when services will be off. Disconnecting and reconnecting plumbing or gas is specialist work that needs a licence regardless of cost (NSW Fair Trading, Home building licence check).
After the stumps are in
- Final levels. The NSW Guide to Standards and Tolerances 2017 treats re-levelled floors after restumping as defective if, within 24 months, they differ by more than 15 mm in any room or 8 mm in any 2 m, unless documented otherwise (NSW Guide to Standards and Tolerances 2017, clause 18.3). Ask for a final level survey.
- Crack repairs. Plaster and cornice cracks are patched once the house has settled into its new levels, often by a plasterer after the restumping crew has left.
- Subfloor ventilation. CSIRO notes that poor subfloor ventilation slows drying under the floor and recommends an adequate system (CSIRO, Foundation Maintenance and Footing Performance); it is easiest to add while the crew is underneath.
- Floor coverings lifted for access go back last.
Restumping and reblocking covers the whole service, published prices are in the underpinning cost guide, and the slab-on-ground equivalent is covered in how long underpinning takes.
FAQs
How long does a full restump take for a three-bedroom house?
whatsthedamage’s national guide puts a standard three-bedroom house with accessible subfloor clearance at about 4 to 7 working days on site, and low-clearance jobs at 7 to 12. Bearer or joist repairs and re-levelling can add to that.
Can restumping be done in winter?
Yes, but wet ground slows subfloor digging, and Wagga averages more rain days in winter than summer. Ask the contractor what weather contingency their timeline includes.
Will water, gas or power be cut off?
Possibly water and gas, where pipes run under the section being lifted; power less often. Ask for the planned disconnections in writing, and make sure a licensed plumber or gasfitter does that part.
Does restumping need council approval?
It depends on the scope and the property. Ask Wagga Wagga City Council or an accredited certifier before work starts, especially for a heritage-listed home.
Sources
- whatsthedamage, Restumping & reblocking cost: time on site, stump counts and subfloor items (updated November 2026); checked 15/11/2026
- BOM, Climate statistics for Wagga Wagga AMO (072150): mean days of rain by month; checked 15/11/2026
- NSW Government, Contracts for residential building work: written contracts, deposit and cooling-off; checked 15/11/2026
- Service NSW, Apply for home building compensation cover: HBC cover; checked 15/11/2026
- NSW Government, Underpinning and piering work: licence threshold; checked 15/11/2026
- Before You Dig Australia, For Homeowners: enquiry response times; checked 15/11/2026
- NSW Fair Trading, Home building licence check: specialist work licensing; checked 15/11/2026
- NSW Government, NSW Guide to Standards and Tolerances 2017 (PDF): floor levels after restumping; checked 15/11/2026
- CSIRO, Foundation Maintenance and Footing Performance (2024, PDF): subfloor ventilation; checked 15/11/2026