A foundation repair runs in a fixed order: inspection, engineering and soil testing where needed, any approvals, quotes and a written contract, the site work, then sign-off and making good. The total time cannot honestly be given as one figure, because it depends on the engineer’s and contractor’s availability and on whether approvals are needed. A few waiting periods are set by NSW rules, and those are the fixed points to plan around.
Step 1: Inspection
A foundation inspection maps the cracks, measures floor levels, checks the subfloor or slab edges and looks at drainage. Its written report says whether the next step is monitoring, an engineer, a soil test or repair quotes. Ask when the report will arrive before booking.
Step 2: Engineer’s report and soil test
For underpinning, and for any repair where a footing has failed, a structural engineer usually diagnoses the cause and specifies the number, position, depth and method of piers. A geotechnical report gives the site’s AS 2870 class; CSIRO notes that “Generally soil classification is provided by a geotechnical report” (CSIRO, Foundation Maintenance and Footing Performance). Contractors can only quote the same job once this scope exists. The guide to the engineer’s report explains what it should contain.
Step 3: Approvals, if any
- Planning approval. Whether underpinning needs approval depends on the scope and the property: ask Council or an accredited certifier before work starts (NSW Planning, Exempt development).
- Heritage. For a heritage item or a building in the Wagga Wagga Conservation Area, minor works can go ahead without consent only once Council has advised in writing, before work starts, that it is satisfied the work is minor or maintenance (Wagga Wagga City Council, Heritage minor works).
- Council sewer and stormwater. Work that could affect Council’s sewer or stormwater drainage, including relocating a drainage line, needs Section 68 approval lodged on the NSW Planning Portal, and building over a Council asset needs a separate encumbrance application (Plumbing Applications, Approvals & Inspections; Building Near Sewer or Stormwater Lines).
Step 4: Quotes, contract and the cooling-off period
Quotes priced from the same engineer’s scope can be compared line by line; published price ranges are in the underpinning cost guide. Then the rules set the pace:
| Rule | Effect on the timeline | Source |
|---|---|---|
| Contract over $5,000 including GST | Must be in writing; deposit must not exceed 10% of the contract price | NSW Government, Contracts for residential building work |
| Contract over $20,000 | Large jobs contract with a five clear business day cooling-off period | NSW Government, Contracts for residential building work |
| Contract price over $20,000, not exempt | Contractor must hold home building compensation cover of at least $340,000 before starting work or taking a deposit | Service NSW, Home building compensation cover |
| Licence | Underpinning and piering over $5,000 including GST needs a contractor licence; check it before signing | NSW Government, Underpinning and piering work |
Step 5: Before digging
Before You Dig Australia gives free plans of gas, electricity, water and telecommunications assets. Its members are “encouraged to respond within 2 business days”, plans expire, and receiving them is not approval to excavate (BYDA, For Homeowners; BYDA FAQs). Where Section 68 approval applies, Wagga Wagga City Council asks for a Notice of Work at least 48 hours before starting and inspections booked at least 48 hours ahead (Plumbing Applications, Approvals & Inspections).
Step 6: Work on site
Time on site depends on the method and the number of piers or stumps. For restumping, whatsthedamage’s national guide (updated November 2026) says a standard three-bedroom house with accessible subfloor clearance takes about “4 to 7 working days on site”, and low-clearance jobs where floorboards must be lifted “7 to 12 working days” (whatsthedamage, Restumping & reblocking cost). Underpinning is covered in how long underpinning takes, and restumping in how long restumping takes. Most of the underpinning process, including staged pits and engineer hold points, happens in this step.
Step 7: Sign-off and final levels
Where an engineer designed the work, ask in the contract for their inspection at the hold points it specifies and a written sign-off at the end. A final floor level survey compared with the first one shows what the lift achieved.
Step 8: Making good
Patching, repointing and painting come last, once the house has had time to show it is stable. CSIRO notes that cracking from construction settlement usually stays unchanged once settlement stops, while cracks from swelling and shrinking can move with the seasons, so a short monitoring period before cosmetic work is reasonable. Ask whether making good is in the quote.
After completion: statutory warranties
In NSW, the contractor is responsible for keeping the work “free of major defects for six years after the work is completed” and for other defects for two years (NSW Government, How to make sure your new building work remains trouble-free, updated 17 September 2026). Keep the contract, engineer’s reports and level surveys together.
FAQs
Can a house be sold while foundation repairs are under way?
It can, but the buyer’s inspector will see the work. The contract and any disclosure should be discussed with a conveyancer or solicitor, with the engineer’s report and contract to hand.
Is there a waiting period after signing a contract?
For contracts over $20,000, NSW rules give a five clear business day cooling-off period, and the deposit is capped at 10% of the contract price whatever the size (NSW Government, Contracts for residential building work).
What if the house moves again after the repair?
Raise it with the contractor in writing promptly. NSW statutory warranties run six years for major defects and two years for other defects from completion; whether new movement is a defect in the work is a question for the engineer.
Sources
- CSIRO, Foundation Maintenance and Footing Performance (2024, PDF): soil classification and how cracking behaves after settlement; checked 15/11/2026
- NSW Planning, Exempt development: approval pathways; checked 16/11/2026
- Wagga Wagga City Council, Heritage minor works: LEP 2010 clause 5.10 (last updated 23 March 2026); checked 15/11/2026
- Wagga Wagga City Council, Plumbing Applications, Approvals & Inspections and Building Near Sewer or Stormwater Lines: Section 68, Notice of Work, encumbrance; checked 16/11/2026
- NSW Government, Contracts for residential building work: contracts, cooling-off and deposit; checked 15/11/2026
- Service NSW, Apply for home building compensation cover: HBC cover; checked 15/11/2026
- NSW Government, Underpinning and piering work: licence threshold; checked 15/11/2026
- Before You Dig Australia, For Homeowners and FAQs: enquiries, response times and limits; checked 15/11/2026
- whatsthedamage, Restumping & reblocking cost: restumping time on site (updated November 2026); checked 15/11/2026
- NSW Government, How to make sure your new building work remains trouble-free: statutory warranty periods (updated 17 September 2026); checked 15/11/2026